Carden Park Playground Renewal Project
Phase 1 of Park Renewal will start February 2010.
We have £50,000 so far (out of £100k needed) to redevelop the park
Phase1: £50k must be spent by April, on equipment & landscaping for ages 8-13.
This will be around the hill in the centre of the park & will start in Feb.
Phase2: we have £40,000 from a large local landfill company for the lower part of the park for ages 0-8.
Work will start on this area in Feb 2010.
Phase3: for ages 13+ will be at the top of the park - we will start applying for funds for this soon.